Insulation of the Strahov Dormitory 

 

Within the framework of the Operational Programme Environment, a project was implemented consisting of insulation of external walls, replacement of windows and doors and damp proofing of the roofs of the Strahov Dormitory blocks 1, 2, 3, 4, 5, 6, 7, 9, and 10. Implementation of the project will lead to decrease of CO2 generation by approximately 267 tons per year and to energy saving in the amount of approximately 4,823 GJ per year. The works will be, naturally, connected with major visual restoration of the blocks concerned. This project is co-funded by the European Union – Cohesion Fund. The period for the project implementation is from 14th February 2015 until 30th September 2015 (Update 28th August).

 

Work time schedule:

Blocks 2, 3, 4, 5, 6, 7

Insulation of the plinth course – will be carried out in the period from 15th February 2015 until approx. 26th July 2015. 

Replacement of windows - will be carried out in the period from 9th March 2015 until approx. 29th April 2015 – the exact time schedule for replacement of windows in the individual rooms will be specified by 23rd February 2015 - READ – NINE POINTS CONCERNING REPLACEMENT OF WINDOWS (pdf).
 Work time schedule (HERE). Update - 20.5.2015 (PDF - only in Czech)

Damp proofing of roofs and terraces - will be carried out in the period from 3rd March 2015 until approx. 24th April 2015.

Mounting of contact insulation system - will be carried out in the period from 16th April 2015 until approx. 6th July 2015. 

 

Block 1

Insulation of the plinth course – will be carried out in the period from 9th February 2015 until approx. 16th July 2015.

Replacement of windows – will be carried out in the period from 11th May 2015 until approx. 7th June 2015.Work time schedule for blocks 9,10,1 HERE (only in Czech). 

Damp proofing of roofs and terraces – will be carried out in the period from 18th April 2015 until approx. 27th May 2015.

Mounting of contact insulation system – will be carried out in the period from 14th May 2015 until approx. 24th July 2015. 

 

Block 9, 10

Insulation of the plinth course – will be carried out in the period from 17th March 2015 until approx. 24th August 2015. 

Replacement of windows – will be carried out in the period from 11th May 2015 until approx. 27th June 2015 –  READ – NINE POINTS CONCERNING REPLACEMENT OF WINDOWS (pdf). Work time schedule for blocks (18. 5. 2015) 9,10,1 HERE and HERE(only in Czech) .

Damp proofing of roofs and terraces – will be carried out in the period from 3rd March 2015 until approx. 24th April 2015.

Mounting of contact insulation system – will be carried out in the period from 25th May 2015 until approx. 14th August 2015. 

 

Additional information

 

  • To all accommodated in blocks 9 and 10 (HERE
  • Further questions regarding the project, discussed and subsequently answered in cooperation with your students’ representatives, can be found (HERE - only in CZECH).